INVESTIGATION OF THE CAUSES OF COST AND SCHEDULE CHANGES IN RESTORATION WORKS OF NATIONAL HISTORIC HERITAGE

Abstract

This study aims to evaluate the accuracy of contractual deadlines in procurement processes for the restoration of national historical heritage. The research consisted of a multiple case study involving three projects contracted by IPHAN, in which inconsistencies were identified between the planned schedules and the actual execution. The budgets and physical-financial schedules included in the bidding processes were analyzed, using SINAPI cost compositions as a reference. These compositions supported the estimation of productivity, while construction site logs were used to identify team composition. Based on this information, the original schedules were revised using MS Project software. The results indicated that the original schedules underestimated the project durations by disregarding key variables, such as actual productivity, team composition, and technical float. The reconstruction of the schedules demonstrated that greater accuracy in initial planning can be achieved, reducing the need for contractual amendments and delays. It is concluded that the adoption of methodologies based on technical data and appropriate planning tools can enhance efficiency, control, and predictability in public restoration projects.

Author Biographies

Daniela Mitiko Nakano Maciel Zoratti, Centro Universitário Filadélfia

Holds a Bachelor's degree in Law from the Pontifical Catholic University of Paraná (PUC/PR). Holds postgraduate specializations in Criminal Procedural Law, Advanced Criminal Practice, and Tax Law from Damásio Educacional. Currently pursuing a Bachelor's degree in Architecture and Urban Planning at Centro Universitário Filadélfia.

João Lucas Pereira dos Santos, Universidade Estadual de Londrina

Civil Engineer, Universidade Estadual de Londrina.

Juliana Prestes Ribeiro de Faria, Universidade Federal de Minas Gerais (UFMG)

PhD in Built Environment and Sustainable Heritage from UFMG.

References

ALI, A. S.; KEONG, C. C.; ZAKARIA, N. A. Issues in building conservation work. Journal of Surveying, Construction and Property, v. 3, n. 2, p. 1-18, 2012.

ASSAF, S. A.; AL-HEJJI, S. Causes of delay in large construction projects. International Journal of Project Management, v. 24, n. 4, p. 349-357, 2006. DOI: https://doi.org/10.1016/j.ijproman.2005.11.010

BECKMAN, P.; BOWLES, G. Building conservation materials. London: Routledge, 2004.

GORI, E. Municipal delays in Italian public restoration projects. International Journal of Heritage Studies, v. 23, n. 1, p. 87-102, 2017.

OLIVEIRA, A. D. Planejamento e controle de obras públicas. Brasília: ENAP, 2009.

REYERS, B. Risk assessment in heritage rehabilitation projects. Construction Economics Journal, v. 9, n. 1, p. 25-34, 2001.

SANTOS, J. P. Análise de desvios em obras públicas. Brasília: Ipea, 2012.

SOUZA, M. E. Orçamento de obras públicas: riscos e controle. Rio de Janeiro: Elsevier, 2006.

How to Cite

Zoratti, D. M. N. M., Santos, J. L. P. dos, & Faria, J. P. R. de. (2026). INVESTIGATION OF THE CAUSES OF COST AND SCHEDULE CHANGES IN RESTORATION WORKS OF NATIONAL HISTORIC HERITAGE. RECIMA21 - Revista Científica Multidisciplinar, 7(7), e778538. https://doi.org/10.47820/recima21.v7i7.8538
Crossmark logo

Similar Articles

You may also start an advanced similarity search for this article.