AUTOMATION OF QUANTITY TAKE-OFF IN A BIM ENVIRONMENT USING DYNAMO AND INTEGRATION WITH SINAPI

Abstract

Quantity take-off for cost estimating still relies, in many workflows, on manual checks, data transfers between software applications, and spreadsheets with limited traceability. This paper presents and evaluates an automated workflow for quantity take-off in a BIM environment using Autodesk Revit, Dynamo, auxiliary Python programming, and spreadsheets organised according to a Work Breakdown Structure (WBS), with services linked to SINAPI. The action research comprised seven stages: modelling, parameterisation, integration with the cost database, automation, WBS organisation, export, and validation. The study was applied to an architectural model of a residential building and compared compound walls with walls modelled as separate layers. Validation addressed traceability, completeness, consistency between units and quantities, reproducibility, technical review, and potential support for resource efficiency. The results showed that standardised parameters enabled the classification of elements and materials, the organisation of quantities by WBS, and the generation of an editable cost-estimate spreadsheet while retaining links to the model. Separate-layer modelling aligned more closely with service decomposition, whereas compound walls simplified modelling. The workflow reduced the need for manual data reorganisation in the cycle examined. Its contribution to sustainability is indirect, because more traceable material inventories may support future estimates of consumption and waste, although environmental performance was not measured. The method therefore provides a reproducible alternative for BIM-based cost estimating.

Author Biographies

Vitor Goes Daros

Master in Applied Engineering and Sustainability, Federal Institute of Education, Science and Technology of Goiás (Instituto Federal Goiano), Rio Verde, Goiás, Brazil.

Idalci Cruvinel dos Reis

PhD in Materials Science, Faculty Member of the Graduate Program in Applied Engineering and Sustainability, Federal Institute of Education, Science and Technology of Goiás (Instituto Federal Goiano), Rio Verde, Goiás, Brazil.

Bacus de Oliveira Nahime

PhD in Materials Science, Faculty Member of the Graduate Program in Applied Engineering and Sustainability, Federal Institute of Education, Science and Technology of Goiás (Instituto Federal Goiano), Rio Verde, Goiás, Brazil.

Marcelo Augusto Rozan dos Santos

PhD in Mechanical Engineering, Full Professor at the University of Rio Verde (Universidade de Rio Verde), Rio Verde, Goiás, Brazil.

Alberto Barella Netto

PhD in Business Administration, Full Professor at the University of Rio Verde (Universidade de Rio Verde), Rio Verde, Goiás, Brazil.

References

ABNT - ASSOCIAÇÃO BRASILEIRA DE NORMAS TÉCNICAS. ABNT NBR ISO 19650-1: Organização e digitalização de informações sobre edifícios e obras de engenharia civil, incluindo BIM - Gestão da informação usando modelagem da informação da construção - Parte 1: Conceitos e princípios. Rio de Janeiro: ABNT, 2019.

AUTODESK. About Compound Walls. Revit 2023 Help. 2023. Disponível em: https://help.autodesk.com/cloudhelp/2023/ENU/Revit-ArchDesign/files/GUID-7657DF90-6AE2-4543-BFDA-7735A8424B1C.htm Acesso em: 8 set. 2026.

ALATHAMNEH, Shadi; COLLINS, Wesley; AZHAR, Salman. BIM-based quantity takeoff: Current state and future opportunities. Automation in Construction, v. 165, p. 105549, set. 2024. DOI: https://doi.org/10.1016/j.autcon.2024.105549

ANDRADE, Felipe Miguel Rocha; BIOTTO, Clarissa Notariano; SERRA, Sheyla Mara Baptista. Modelagem BIM para orçamentação com uso do SINAPI. Gestão & Tecnologia de Projetos, v. 16, n. 2, p. 93–111, 12 mar. 2021. DOI: https://doi.org/10.11606/gtp.v16i2.170318

CAIXA ECONÔMICA FEDERAL. SINAPI - Sistema Nacional de Pesquisa de Custos e Índices da Construção Civil: metodologia e conceitos. Brasília: Caixa Econômica Federal, 2023.

CHAREF, Rabia; ALAKA, Hafiz; EMMITT, Stephen. Beyond the third dimension of BIM: A systematic review of literature and assessment of professional views. Journal of Building Engineering, v. 19, p. 242–257, set. 2018. DOI: https://doi.org/10.1016/j.jobe.2018.04.028

EASTMAN, C.; TEICHOLZ, P.; SACKS, R.; LISTON, K. Manual de BIM: um guia de modelagem da informação da construção para arquitetura, engenharia, construção e gestão. Porto Alegre: Bookman, 2014.

GUERRA, Beatriz C.; BAKCHAN, Amal; LEITE, Fernanda; FAUST, Kasey M. BIM-based automated construction waste estimation algorithms: The case of concrete and drywall waste streams. Waste Management, v. 87, p. 825-832, 2019 DOI: https://doi.org/10.1016/j.wasman.2019.03.010 DOI: https://doi.org/10.1016/j.wasman.2019.03.010

KHOSAKITCHALERT, Chavanont; YABUKI, Nobuyoshi; FUKUDA, Tomohiro. Improving the accuracy of BIM-based quantity takeoff for compound elements. Automation in Construction, v. 106, 102891, 2019 DOI: https://doi.org/10.1016/j.autcon.2019.102891 DOI: https://doi.org/10.1016/j.autcon.2019.102891

KHOSAKITCHALERT, Chavanont; YABUKI, Nobuyoshi; FUKUDA, Tomohiro. Automated modification of compound elements for accurate BIM-based quantity takeoff. Automation in Construction, v. 113, 103142, 2020 DOI: https://doi.org/10.1016/j.autcon.2020.103142 DOI: https://doi.org/10.1016/j.autcon.2020.103142

LIN, Y. H.; KHONGSOMCHIT, L.; KAEWUNRUEN, S.; PLUMMER, P. Challenges and barriers in BIM adoption and implementation in railways. Frontiers in Built Environment, v. 11, p. 1-20, 2025. DOI: https://doi.org/10.3389/fbuil.2025.1714009

LOURENÇO, M. P.; ARANTES, A.; COSTA, A. A. Barriers to Building Information Modeling (BIM) Implementation in Late-Adopting EU Countries: The Case of Portugal. Buildings, v. 15, p. 1-22, 2025. DOI: https://doi.org/10.3390/buildings15101651

MACCARINI, Helena Somer; FRASSON, Diego Dagostin; ANTUNES, Elaine Guglielmi Pavei; CRISTIAN, Aurio Damasio. Análise comparativa entre modelagem por paredes compostas com aplicação de peças e modelagem por camadas separadas em BIM: estudos de caso. Revista Técnico-Científica de Engenharia Civil Unesc, v. 7, n. 2, 2022 DOI: https://doi.org/10.18616/civiltec.v7i2.6778 DOI: https://doi.org/10.18616/civiltec.v7i2.6778

MONTEIRO, André; MARTINS, João Poças. A survey on modeling guidelines for quantity takeoff-oriented BIM-based design. Automation in Construction, v. 35, p. 238-253, 2013 DOI: https://doi.org/10.1016/j.autcon.2013.05.005 DOI: https://doi.org/10.1016/j.autcon.2013.05.005

SEGHIER, Taki Eddine et al. From BIM to computational BIM: A systematic review of visual programming application in building research. Ain Shams Engineering Journal, v. 16, n. 1, p. 103173, jan. 2025. DOI: https://doi.org/10.1016/j.asej.2024.103173

SOUSA, P. R.; MULLER, B. M. Desafios e barreiras do BIM e do Lean na construção civil brasileira. Revista Pensamento Contemporâneo em Administração, v. 16, n. 3, p. 181-198, 2022. DOI: https://doi.org/10.12712/rpca.v16i3.54259

SUCCAR, B. Building Information Modelling framework: a strategic approach to industry migration. Automation in Construction, v. 18, n. 3, p. 357-375, 2009. DOI: https://doi.org/10.1016/j.autcon.2008.10.003

THIOLLENT, M. Metodologia da pesquisa-ação. 18. ed. São Paulo: Cortez, 2011.

TRAN, Thai Bao et al. An Integrated BIM-Based Application for Automating the Conceptual Design for Vietnamese Vernacular Architecture: Using Revit and Dynamo. Applied Sciences, v. 15, n. 12, p. 6776, 16 jun. 2025. DOI: https://doi.org/10.3390/app15126776

TRIPP, D. Pesquisa-ação: uma introdução metodológica. Educação e Pesquisa, São Paulo, v. 31, n. 3, p. 443-466, 2005. DOI: https://doi.org/10.1590/S1517-97022005000300009

How to Cite

Daros, V. G., Reis, I. C. dos, Nahime, B. de O., Santos, M. A. R. dos, & Barella Netto, A. (2026). AUTOMATION OF QUANTITY TAKE-OFF IN A BIM ENVIRONMENT USING DYNAMO AND INTEGRATION WITH SINAPI. RECIMA21 - Revista Científica Multidisciplinar, 7(11), e7119232. https://doi.org/10.47820/recima21.v7i11.9232
Crossmark logo